When should you order for Chinese New Year 2027?
Chinese New Year 2027 falls on 6 February. Sellers, domestic delivery, warehouse packing, and international uplift usually slow earlier. Use one planning model, then confirm the live route.

Fishgoo Buying Team.
Chinese New Year 2027 falls on 2027-02-06, a Saturday. That date is the first day of the lunar year in this planner. It is not the State Council's statutory holiday table, and it is not a seller, courier, or warehouse cutoff.
Orders usually need to move earlier because the work happens in sequence. Custom and wholesale goods slow first, while the seller is still making or packing them. A domestic courier then has to bring the parcel to the warehouse, and that hop often takes longer in the weeks before the holiday. Warehouse photo checks and consolidation queues grow when many buyers ship at once. International uplift is last, and tight air space can slow a handoff or raise the seasonal rate. None of those steps has an official close date on this page.
Why 6 February is not your order deadline
Plan backwards from the day you want the parcel, not from the holiday morning.
- Seller preparation comes first. A custom or made-to-order 1688 piece needs more seller days than an in-stock Taobao listing. Start that order first. This page does not publish a factory-close date.
- Domestic transport is next. Late January is when seller-to-warehouse trips commonly stretch.
- Warehouse QC and consolidation come after the item arrives. A late rush means a longer queue to photograph, approve, and pack.
- International transport is last. Compare a current route before you pay. This planner does not quote freight.

If one seller is late, ship what is ready and leave the late piece. Fishgoo includes 100 days of free storage and 5 free QC photos per item. Storage is time at the warehouse, not a promise that an item cannot be lost. A QC photo is a warehouse view, not an authenticity certificate. The purchasing service fee on published Fishgoo terms is 0, and there are 2,000+ routes. You can also ask the seller a question through the buying team, consolidate several sellers, or ask them to bargain.
A planning window from one model
The dates in the box are planning assumptions from the same model as the calculator. They are not a Fishgoo warehouse confirmation and not a carrier notice. If you change the arrival date, destination, route, or order type, the calculator updates those dates with that same model.
For the default inputs in this model (needed by 2027-02-14, US, DDP air, configured max 14 days, Taobao in-stock, 5 seller days), order by 2027-01-18 and submit the parcel by 2027-01-26. These are planning assumptions from the model, not a Fishgoo warehouse confirmation or a carrier notice.
If that order date has already passed, the same model shows a post-holiday planning resume of 2027-02-16. That resume date is an assumption in the model, not a confirmed return to work and not a booked flight.
| Needed by | Planning order | Planning submission |
|---|---|---|
| 2027-02-05 | 2027-01-12 | 2027-01-17 |
| 2027-02-14 | 2027-01-18 | 2027-01-26 |
| 2027-02-28 | 2027-01-18 | 2027-01-27 |
CNY 2027 cutoff planner
| Field | Sample plan |
|---|---|
| Status | Planning window is open |
| As of | 2026-11-27 Asia/Shanghai |
| Target arrival | 2027-02-14 |
| Destination | US |
| Route tier | DDP air, configured max 14 days, max 14 days |
| Order type | Taobao in-stock, 5 seller days |
| Last order date | 2027-01-18 |
| Last parcel submission | 2027-01-26 |
| Packing days used | 3 |
| Warehouse cap | No |
| Seller cap | Yes |
| Model note | Destination is stored on the plan. This model does not add extra country days beyond the route tier. |
Preset dates at the same route and order type
| Needed by | Last order | Last submission | Status |
|---|---|---|---|
| 2027-02-05 | 2027-01-12 | 2027-01-17 | Planning window is open |
| 2027-02-14 | 2027-01-18 | 2027-01-26 | Planning window is open |
| 2027-02-28 | 2027-01-18 | 2027-01-27 | Planning window is open |
Open the shipping cost estimatorPaste a product linkRead the 100-day storage guide
To confirm a date before you pay for international dispatch, read the seller's dispatch note, the warehouse instructions on the parcel screen, and a current route on the shipping cost estimator. This page cannot confirm those live instructions for you.
What to do with the window
- Order the slow item first. A custom or pre-order piece is the one most likely to miss the window.
- If one seller is late, split the parcel and use the 100-day storage guide for the piece that is not ready.
- Review the QC photos while the seller can still answer.
- For freight, use the shipping cost estimator. For how a haul is usually packed, see how to plan a haul.
Questions
Is 2027-02-06 the last day to order? No. That is the lunar new year day used here, not the last seller, courier, or warehouse day. The model above prints an earlier planning order date and an earlier planning submission date.
Will the warehouse accept the parcel on the printed submission date? Not confirmed by this page. Check the warehouse instructions before you pay for international dispatch.
What if the order date has already passed? The model marks a closed window and can show a post-holiday planning resume date. That resume date is an assumption in the model, not a booked flight or a confirmed return to work. The storage guide explains the 100 free days while you wait.